Skip To Main Content

translate-container mobile-version

mobile-header-portals-nav

mobile-staff-nav

mobile-district-nav

mobile-student-nav

mobile-header-calendar-icon

mobile-main-nav

header-container

logo-container

logo-image

logo-title

right-container

right-top-container

translate-container desktop-version

header-portals-nav

staff-nav

staff-menu

district-nav

student-nav-trigger

students-menu

header-calendar-icon

search-container

right-bottom-container

horizontal-nav

Breadcrumb

Lake Washington High School Addition

Block 7: Occupancy

 

Lake Washington High School classroom addition


 

Project updates

LWHS world class learning environment new additions video

Thanks to the 2019 Capital Construction Levy, Lake Washington High School has completed projects to add more space for students in class, in the new auxiliary gym and while they are in the commons area. 

The new North Wing on campus added 20 new “world class” classrooms and shared space. The new classrooms were built with a focus on math, science, and Career and Technical Education (CTE) classes.

In April 2019, voters approved a capital construction levy that is providing $120 million in funding, collected over six years. These funds, combined with state construction assistance funds, will provide a total of $144 million. As of March 2021, $73 million has been spent on these levy projects:

Twain Elementary 2021 update

Workers are in the process of installing the wood floor at the new auxiliary gymnasium at Lake Washington High School. Sprinkler and electrical installation have begun and interior painting is underway. The school will be able to start using the gym for physical education classes and other athletic needs in the fall.

Exterior glass and brick

The roof installation at Lake Washington High School auxiliary gymnasium is complete, protecting the building from rain and other weather. Exterior walls, including brick, concrete masonry, and the glass/aluminum wall system are installed, which will allow interior construction to progress. Circular solar tubes reflect light into the gym naturally during the day. Installation of interior building systems – including electrical, data, plumbing and mechanical – is in progress. The gym is scheduled to open in fall 2021.

LWHS gym construction

The auxiliary gymnasium construction is on schedule at Lake Washington High School. An expanded locker room was completed in December in the main gymnasium next door in order to provide

Progress photos

 


Aerial photos




Drawings and site plans

 

Project information

Architect: McGranahan Architecture
Contractor: Lydig Construction
Location: 12033 NE 80th St, Kirkland, WA 98033
Spaces: 20 classrooms, including general, science, CTE and teacher planning spaces; auxiliary gymnasium and commons space.
Current Portables: 10 classroom portables currently at LWHS will be relocated to Rose Hill Middle School, Kirkland Middle School and Inglewood Middle School after construction.
Planned opening: New classrooms: Fall 2020; Auxiliary gymnasium and commons space: Fall 2021.