Margaret Mead Elementary School
Margaret Mead Elementary Grand Opening
Project Updates
In April 2019, voters approved a capital construction levy that is providing $120 million in funding, collected over six years. These funds, combined with state construction assistance funds, will provide a total of $144 million. As of March 2021, $73 million has been spent on these levy projects:
On May 4, LWSD closed on a 25-acre property in Redmond, which was formerly owned by Cadman. The site is within King County’s Urban Growth Boundary and adjacent to a growing residential neighborhood.
Homes around the district received LWSD’s Building on Success progress newsletter in their mailboxes in February. If you missed it, you can view the digital version, which includes these updates:
After more than a year of work, the LWSD Facilities Advisory Committee (FAC) addressed the Board on January 25 during its regular meeting. The FAC was tasked with making recommendations to accommodate the District’s rapid enrollment growth and continue to provide quality learning environments. The Board will use the recommendations to determine next steps, which could include sending a funding measure to voters in 2022.
You can see the final recommendations report and the FAC’s presentation to the Board here:
We are so pleased that all our bond projects are now completed and ready for students. We want to thank the community for their continued support in building needed classroom space. While spending will still occur over the next year as we close out the projects, the charts below show planned 2016 bond program revenues and expenditures compared to current receipts and spending. Of the total planned revenues and expenditures of $434 million has been received to date. Of the total planned revenues and expenditures of $434 million that has been received to date, the district has spent $409 million.
Progress Photos
Aerial Photos
Drawings and site plans
Project Information
This project will rebuild and enlarge Margaret Mead Elementary School. The Long-Term Facilities Task Force recommended this project.
Architect: BLRB Architects
Contractor: Lease Crutcher Lewis
Square Footage: 78,000
Capacity: 690 students
Spaces: 30 standard classrooms plus music, art/science rooms, ELL/SN/special education, library, cafeteria/commons, gymnasium, and outdoor covered play area
Estimated Project Cost: $44,987,000 (Includes construction costs of $26.5 million 2016 dollars, $12.7 million in non-construction costs, and $5.7 million in expected construction inflation)
Planned opening: September 2019
Remodel vs. Rebuild
A Remodel vs Rebuild Study concluded rebuilding a new school would be more cost effective than remodeling and enlarging the existing school. The current school consists of multiple small buildings made of cinder block. A new building would bring the entire school under one roof and limit access points into the building to enhance safety.
State construction assistance: Due to its age, the school became eligible for state funds for renovation or replacement in 2009. The district expects to receive $3 million in State Construction Funding Assistance for this project.
Sign up to receive email updates about this project.