News

Seahawk Blitz joins the Muir Elementary Turkey Trot

It was all smiles and high fives at John Muir Elementary when the Seahawk Blitz joined students at the 17th Annual Turkey Trot. This event took place during lunch recesses and promotes the importance of physical fitness and activity.

Events

Twitter

Frequently Asked Questions

Frequently asked questions about the project to rebuild and enlarge Juanita High School

The project to rebuild and expand Juanita High School's (JHS) academic building is funded by a $398 million construction bond, approved by voters in April 2016. The bond funds eight school projects in total. These schools will help serve the rapid enrollment growth in Lake Washington School District (LWSD).

LWSD has actively engaged staff and community throughout the JHS design process. This page provides responses to the questions that were most frequently asked during staff and community meetings and via the Let’s Talk online system. As information is updated or added, we will include the date of the change next to the question.

If you have more questions or comments, please contact us via the Let’s Talk online system.

Access to and schedule for the administration offices

Will the administration office be open during the summer, and where will it be located?

Yes, the administration office will be open per the schedule listed below. Signage will be posted that states the location and directions to the office.

Juanita High School Summer 2017 – Administration/Main Office Hours – 425-936-1600

DatesLocationHours
July 26
Portable #327
Located near SE entrance off NE 128th
8:00 a.m. - 12:00 p.m.
July 31 - August 4Portable #3278:00 a.m. - 12:00 p.m.
August 7 - August 11Portable #3278:00 a.m. - 12:00 p.m.
August 14 - August 18Portable #3278:00 a.m. - 1:00 p.m.
August 21 - August 25Portable #3278:00 a.m. - 1:00 p.m.
August 28 - September 1

Beginning August 28, the administration will move to a
portable situated on the tennis courts in the NW area of the
site. More information will be provided as soon as possible.

8:00 a.m. - 1:00 p.m.
September 4Labor Day - Administration office will be closedClosed for holiday
September 5First Day of School - Administration office will be in a
portable situated on the tennis courts in the NW area of the site. Portable number will be provided as soon as possible.
Regular office hours: 7:00 a.m. - 3:00 p.m.

Schedules for the 2017-18 school year will be available on the JHS website.

Student Prep Days
Wednesday and Thursday, August 30 and 31
8:00 a.m. - 3:00 p.m.

Orientation - Fall 2017

Construction Phases

Construction work on the Juanita High School project is phased. What will be done during each phase?

Summer 2017 – Fall 2019
The district accelerated the schedule and began work in June 2017. This early start allows the school to open in 2020, one year earlier than planned.

  • Construction began in June 2017
  • The administration wing was demolished in July 2017. Administration is housed in a portable on the tennis courts, located at the Northwest corner of the JHS site.
  • In August 2017, 12 portables were moved to the tennis court, tennis courts close.
  • Fieldhouse and athletic fields remain available for use by JHS; access by other organizations will be limited
  • Swimming pool remains open for use by the school and by the community

Fall 2017 – Spring 2018

  • No construction activity during this time

Spring 2018 – Spring 2019

  • Construction work resumes in April 2018
  • North parking lot closes on April 2, 2018
  • The theatre will be demolished in June 2018, after the 2017-18 school year is completed
  • The North wing will be demolished in Summer 2018
  • Four additional portables will be moved to the tennis courts in Summer 2018
  • The East parking lot closes in April 2018

Summer 2019 – Fall 2020

  • Remaining portions of the current school building will be demolished in summer 2019
  • Six portables will be removed in Fall 2019 leaving 10 portables
  • North parking lot reopens in Fall 2019
  • Theatre opens in early 2020
  • Remaining portables are removed from the site in Summer 2020
  • Construction on the school ends in August 2020, some site work continues
  • East parking lot reopens in Fall 2020
  • The school is complete and open to students and staff in Fall 2020

Fall 2020 – Winter 2021

  • Tennis courts are restored in early 2021
  • Final site work is completed

Safety

How will construction personnel be identified?

Construction workers can be identified by the protective gear they wear, such as a high visibility safety vest and hard hat. All construction workers are required to check in with the construction site superintendent immediately upon arrival at the job site each day and as they leave for the day. The contractor keeps a log of all employees who are on site.

What measures will be in place to protect students, staff and visitors from construction activities, and to provide for safe navigation around the site?

A safety officer will always be on site during construction activities to actively monitor safe work practices, including measures that protect pedestrian safety. When staff and students return in the fall of 2017, the construction area will be fenced off from other parts of the campus. Only authorized persons will be able to access the work site. Clear signage will identify pedestrian pathways.

In addition, structural walls, will separate the occupied portions of the school from construction activities. One wall will be placed at the point where the west wing (from the main office and south) is detached from the rest of the building.

The contractor has an excellent safety record and follows all applicable Occupational Safety and Health Administration (OSHA) and Washington Industrial Safety and Health Act (WISHA) regulations.

Is there a process in place for criminal background checks for construction personnel working on the site?

Yes. The construction contract requires background checks and drug testing. The contractor is also required to enforce good workplace behavior among all project personnel.

Are there hazardous materials in the building such as asbestos and lead paint?

Yes. Some regulated materials were used in the building before codes were updated. We asked a third party to conduct a complete assessment of the type and location of regulated materials in the building. The contractor is required to follow all regulations for the removal of regulated materials prior to building demolition. The contractor will follow all regulations specified by the appropriate state agency. We plan for this work to occur when students and staff are not on campus.

Signage on campus

Will there be vehicular and pedestrian signage to help with outdoor directions between portables and the main building?

Yes. Vehicular and pedestrian signage will be installed around campus to provide directions. This will clearly separate school activity from contractor activity. Work areas will be clearly marked as off limits to anyone other than authorized personnel. This signage will be in place before staff and students return to campus for the 2017-18 school year. As the project progresses, signage will be moved and/or added.

Will passing periods be extended to allow for students to move to and from portables to the furthest point in the main building?

Distances across campus during construction will be about the same as current walk routes. There is not a plan to extend the time for passing periods. However, to allow for students to become acquainted with the campus, an additional grace period for arrival at the next class will be granted at the beginning of the school year. School administrators and teachers will advise students of the policies.

Learning environment

How will a standard portable classroom be set up? Will students have access to technology in the portables as they do now in the main building classrooms?

The portable classrooms will be set up per district standards.When classrooms move to a portable, technology equipment will also be moved, along with furniture and other items. The classroom technology in portables includes the projection equipment, active board, speaker system and teaching station. The infrastructure to support wireless internet will also be available.

Will tests such as the Scholastic Aptitude Test (SAT), College Readiness Assessment (ACT), Advanced Placement (AP), Cambridge and other state testing be impacted by the construction?

Maintaining a supportive learning environment is a top priority for administrators and the construction project team. Testing will continue to take place on site. Certain construction activities will be scheduled so that impact to the learning environment is minimized, to the extent possible. Special consideration will be given to the timing of testing periods.

If areas where testing is typically held are affected by construction activity, the school will plan for alternate testing locations.

What steps is the project team taking to mitigate construction noise and activity to avoid negative impact to the learning environment?

Phasing of the project allows for the "noisy" demolition work to take place during summer months when students and staff are not present. The project team is working closely with school administration to ensure a good learning environment.

Will there be enough restrooms for students and staff during each phase?

Yes. The building code specifies how many restrooms must be available for the number of students and staff that occupy the site. We follow these requirements. During the summer of 2017, a restroom trailer will be added on site for students and staff who occupy the portables. Restrooms will also be available in the main building.

Programs, services, and events

The theater and performing arts spaces will be demolished and will not be available from the start of summer break in 2018 through the end of August 2019. Where will these activities be held?

Drama classes will be held at JHS during construction. Performances will be off-site. The administration is in the process of identifying alternative off-site performance venues, and will announce the locations when they are determined.

Where will the other music programs, currently held in the performance arts wing, be held during construction?

Classes will be held on-site during construction. The current performing arts wing will be in place during most of the 2017-18 school year. Performances after this time will be off-site. School administrators are working to find the best place(s) to hold our music performances from 2018-2020. The school will announce the decisions as they are made.

Will the counseling and career center be relocated for temporary use when it is impacted by the construction?

Yes. The project team is planning for the temporary relocation of these services, most likely in the main building.

Where will tennis practice take place while the tennis court area is used for temporary portables?

The JHS tennis program is relocating to Lake Washington High School (LWHS) for the duration of the construction period. The administration is coordinating schedules to ensure that there is adequate space at LWHS. Tennis team members will receive more information directly from JHS administration. LWHS is located at 12033 N.E. 80th ST, Kirkland.

Will any part of the campus be open for outside building use once construction begins, or will it be closed to all outside groups during the construction period?

During the construction period access by outside groups to Juanita High School facilities will be limited. We look forward to working with outside groups once construction is complete in 2020.

How will the field house and athletic fields be affected by construction?

Access by outside groups to the field house and athletic fields will be limited during construction. (July 2017 – Fall 2020). Juanita High School classes and teams will continue to use the facilities.

It is possible that there will be intermittent, temporary traffic and parking interruptions during construction. This may be necessary to accommodate large deliveries to the site or due to needed power or other utility interruptions.

Will the pool be available at all regularly scheduled times, or will access be interrupted? What is the impact to the Wave Aquatics program, including parking?

In general, the pool and the Wave Aquatics program will be available throughout the construction period, 2017–2020. There may be intermittent, temporary traffic and parking interruptions to accommodate large deliveries to the site or due to utility work. JHS will avoid disruption to pool availability, to the extent possible. We will coordinate any disruption to pool operation with Wave Aquatics.

Will the STEM shuttle continue service to and from JHS?

No. The STEM shuttle will be relocated from JHS to other location(s) starting in the fall of the 2017-18 school year until the fall of the 2020-21 school year. A site has not yet been identified. When a site has been selected, it will be announced prior to September 2017.

Traffic flow and parking on campus

How will student drop-off and traffic circulation (by bus and by car) be affected by each phase?

The project team is working closely with the JHS administration to specify the drop-off/pick-up locations and general traffic circulation on campus. This information will be shared before school starts. Site signage will provide direction for student drop-off and pick up.

When the number of parking spaces is reduced by approximately one half, how will parking impacts be mitigated?

Currently, there are around 629 parking spaces available on campus. Parking availability will decrease/increase per the phases of the school.

  • The current number of parking spaces will be available until the beginning of Spring Break in 2018 (April 2, 2018).
  • The North parking lot (204 spaces) will close at the beginning of Spring Break (April 2, 2018), leaving 425 parking spaces.
  • The East parking lot (64 spaces) will close in the fall of 2018, leaving 361 spaces on campus.

Students are encouraged to carpool or take the bus to help minimize traffic and parking on site.

JHS administrators and the construction project team are working to identify options and solutions. Information about parking will be shared as decisions are made, and as far in advance of closures as possible.

We estimate that the North lot will reopen in fall 2019 (adding back 204 spaces), and that the East lot will reopen in the fall of 2020 (adding back an additional 64 spaces).