Carson Elementary
Planning & Design – Completed
Construction Begins – Completed
Move in – Fall 2008
Frost Elementary
Planning & Design – Completed
Construction Begins – Completed
Move in – Fall 2009
Lake Washington High School/Northstar Junior High
Planning & Design – Completed
Construction Begins – Spring 2009
Move in – Fall 2011
Finn Hill Junior High/Environmental & Adventure School
Planning & Design – Completed
Construction Begins – Summer 2010
Move in – Fall 2011
Muir Elementary
Planning & Design – Spring 2008
Construction Begins – Summer 2010
Move in – Fall 2012
Keller Elementary
Planning & Design – Spring 2010
Construction Begins – Spring 2012
Move in – Fall 2012
Sandburg Elementary/Discovery Community School
Planning & Design – Spring 2009
Construction Begins – Spring 2011
Move in – Fall 2012
Rose Hill Junior High/Stella Schola Middle School
Planning & Design – Fall 2009
Construction Begins – Spring 2011
Move in – Fall 2013
Bell Elementary
Planning & Design – Spring 2010
Construction Begins – Spring 2012
Move in – Fall 2013
Rush Elementary
Planning & Design – Spring 2009
Construction Begins – Spring 2011
Move in – Fall 2013
International Community School/Community School
Planning & Design – Fall 2011
Construction Begins – Summer 2012
Move in – Fall 2013