2016 Bond School Construction Projects 

​The projects on this page have been funded by the 2016 bond measure.

2016 Bond Projects - Program Schedule
2016 Bond Construction Project Schedule
Click here for a printable version of the program schedule

New School Projects  

New Middle School – Redmond Ridge
Click here for more information.

 

Project Information
Location: Redmond Ridge Drive NE and NE 99th Place, Redmond Ridge East
Square Footage: 134,000
Capacity: ​900 students
​Spaces: 24 standard classrooms, instrumental and vocal music, special education, art, lab science, CTE, library, cafeteria/commons with stage, and gymnasium
​Estimated Project Cost: $77,592,000
​Planned Opening: 2019
Neighborhood boundaries: ​Boundaries will be developed in a process including public feedback during the 2018-19 school year.

New Elementary School – North Redmond
Click here for more information.

 Drawing of new elementary school in north Redmond


Project Information
Location: 172nd NE and NE 122nd, Redmond
Square Footage: 78,000
Capacity: ​550 students
​Spaces: 30 standard classrooms plus music, art/science rooms, ELL/SN/special education, library, cafeteria/commons, gymnasium, and outdoor covered play area
​Estimated Project Cost: $43,257,000
​Planned Opening: 2018
Neighborhood boundaries: ​Boundaries will be developed in a process including public feedback during the 2017-18 school year.

New Elementary School – Redmond Ridge East
Click here for more information.

 



Project Information
Location: Eastridge Drive NE, Redmond Ridge East
Square Footage: 78,000
Capacity: ​550 students
​Spaces: 30 standard classrooms plus music, art/science rooms, ELL/SN/special education, library, cafeteria/commons, gymnasium, and outdoor covered play area
​Estimated Project Cost: $43,257,000
​Planned Opening: 2018
​​Neighborhood boundaries: ​​Boundaries will be developed in a process including public feedback during the 2017-18 school year.

Aging Schools

Juanita High School
Click here for more information.

Project Information
Location: 10601 NE 132nd Street, Kirkland
Square Footage: 217,000
*Field House & Pool remain "as is"
Capacity: 1,800 students (increase of 504)
​Spaces: 36 standard classrooms plus science labs, art, CTE, special education, instrumental and vocal music, library, theater, cafeteria
​Estimated Project Cost: $145,477,000
​Planned Opening: 2021

Peter Kirk Elementary School
Click here for more information.

Project Information
Location: 1312 6th Street, Kirkland
Square Footage: 78,000
Capacity: 550 students (increase of 190 based on K-3 class size reduction)
​Spaces: 30 standard classrooms plus music, art/science rooms, ELL/SN/special education, library, cafeteria/commons, gymnasium, and outdoor covered play area
​Estimated Project Cost: $44,987,000
​Planned Opening: 2019

Margaret Mead Elementary School
Click here for more information.



Project Information
​Location: 1725 216th Ave NE, Sammamish
Square Footage: ​78,000
Capacity: 550 students (increase of 158 based on K-3 class size reduction)
Spaces: 30 standard classrooms plus music, art/science rooms, ELL/SN/special education, library, cafeteria/commons, gymnasium, and outdoor covered play area
Estimated Project Cost: $44,987,000
Planned Opening: 2019

Other Projects

Explorer Community School
Click here for more information.

Project Information
Location: 7040 208th Ave NE, Redmond (at Dickinson Elementary)
Square Footage: 3,000
Capacity: 75 students
​Spaces: 4 modular, including 3 standard classrooms and support space
​Estimated Project Cost: $1,664,000
​Planned Opening: 2017

Old Redmond School House
Click here for more information.

Project Information
Location: 16600 NE 80th ST, Redmond
Square Footage: 40,000
​Spaces: 10 preschool classrooms, gymnasium, cafeteria / commons
​Estimated Project Cost: $7,837,000
​Planned Opening: 2019
How Do I...
 

 Have any questions?

 

​Let's Talk! Click here to ask questions about the 2016 Bond school construction projects.

 